- deployed new FR app
Submit – should be enabled when everything is complete, sets the status to SubmittedComments/Approval Status should be visible to user, not editable- Point of Contact doesn’t seem to get saved on add
Contract Details should not show add Contracts when the second question is no, just set the contract to TBDRemove Contract Number from Government Labor, Travel, Equipment/MaterialsSum of Direct Cite and Reimbursable should equal to Funding Amount, add warning to Funding Details- Sum of all Funding Break down should not be greater than the Funding Amount
- FDRCC STE Count should be blank, not 0
- Change Contract Process to Invoice Processing
- Invoice Instruction required for all in Invoice Processing
- Project Number not required in ISR PMO, add TBD
- Req # not required in ISR PMO
- working through the notes from today….