Phil 6.2.2010

7:30 – 2:30 (VISIBILITY)

  • Talked to JM:
    • Running the system on the appropriate servers by July
    • Adding project management capability
  • Talked to JW about documentation
  • Having Tom set up VISIBILITY, Scripting, and ProjPortfolio on viz-n
  • Laid out some of the issues about getting the Network widget into VISIBILITY, and did a little roadmapping on future work
  • Pinged Ken Beckman about how the install was coming

2:30 – 3:30 (FP)

  • Added in the sensors and set up the motor to hold the bar in place, but the readings aren’t shifting much.